Our Products

Home  |  Our Products

Have a question? Write to us!

* Required Field
  1. 2 KG Retail Pack

  2. 20 KG RETAIL Pack

Key Points to Remember

  • Add powder to water and not water to powder
  • Approx. 14 liters water should be used for making mix of one bag of 20 kg
  • Surface should be properly cleaned before applying P.O.P.
  • Wet the surface for 10 minutes before applying P.O.P.
  • Hands should be completely dried while taking out P.O.P. from the bag

Technical Specifications

PARTICULARS REQUIREMENT AS PER IS:2547
(Part-1)-1976 Type A
OUR RESULT
A.CHEMICAL REQUIREMENTS    
1.Sulphuric Anhydride(SO3) % Mass 35 minimum 40-45
2.Calcium Oxide(CaO) % by Mass 2/3 of SO3 28-35
3.Soluble Magnesium Salt expressed as % of MgO 0.2 Max 0.15
4.Total loss on ignition % by mass Not greater than 9%
and not less than 4%
4.5-7.5
B.PHYSICAL REQUIREMENTS    
1.Setting time(neat plaster) minutes 20-40 minutes 20-30
2.Transverse strength(kg/cm2) 5 minimum 10-15
3.Residue on 90 micron sieve(% by weight) 3.50 3-4

Remarks: - The sample conforms to IS-2547(Part-1) 1976 for Gypsum Building Plaster of Paris (Type-A) Beta hemihydrate for Chemical Test with respect to above tests.